Windows have been installed and gutters placed.
A blog that tracks our building process with Wisdom Homes in Georges Fair from the purchase of the land until handover of the completed home.
Thursday, 20 December 2012
Wednesday, 12 December 2012
Water and gas pipes are in
Saturday, 8 December 2012
Frame has begun
Went past today and saw that the frames were up. Just need a few more boards and the windows and the frame will be complete.
Tuesday, 4 December 2012
Plumbing!
Visited today and got to see some excavation occurring for our plumbing. View is from the back of our lot.
Saturday, 1 December 2012
Slab poured
Our slab was poured last Tuesday and we went out to the site today to have a look. Quite exciting to see it there. We were also contacted by our Site Supervisor on Friday to let us know plumbing would be done on Tuesday and our Frame is set to start on Wednesday. Progressing nicely!