A blog that tracks our building process with Wisdom Homes in Georges Fair from the purchase of the land until handover of the completed home.
Thursday, 28 February 2013
Saturday, 23 February 2013
Gyprock completed
Got a fantastic update from our site supervisor today. The walls and ceilings are in. We will be at lock up stage next week.
Thursday, 14 February 2013
Eaves installed, bricks cleaned, and electricals started
The eaves have now been installed around the home, and the bricks have been cleaned. Looking more like a house. Also noticed that electrical wiring has been installed.
Sunday, 10 February 2013
Exterior being finished this week
Site supervisor called me on Friday to confirm that the bricks were completed. Mentioned that the plans this coming week are for the eaves to be put in on Monday and bricks to be cleaned on Thursday.
Drove past on Saturday and also noticed that the air conditioning ducting and electrical wiring has been installed. Can't wait for interiors to start.
Drove past on Saturday and also noticed that the air conditioning ducting and electrical wiring has been installed. Can't wait for interiors to start.
Wednesday, 6 February 2013
Bricks completed
The bricking has completed. The piers are up and our windows have had the bricks added to the sills.
Monday, 4 February 2013
Bricks almost completed
Visited today to see that all that is left to be bricked is the porch. If we're lucky we could have a house that can resist the elements by end of this week.