The bricking has completed. The piers are up and our windows have had the bricks added to the sills.
A blog that tracks our building process with Wisdom Homes in Georges Fair from the purchase of the land until handover of the completed home.
Wednesday, 6 February 2013
Monday, 4 February 2013
Bricks almost completed
Visited today to see that all that is left to be bricked is the porch. If we're lucky we could have a house that can resist the elements by end of this week.
Wednesday, 30 January 2013
Another wall bricked
Our back wall has almost been entirely bricked and progress has been made on our other side wall. Should be fully bricked by Friday at this rate. Exciting! :-)
We also received our first water bill today (not really that exciting).
We also received our first water bill today (not really that exciting).
Sunday, 27 January 2013
Wednesday, 23 January 2013
Bricks have arrived!
Finally our bricks have arrived on site and the garage side wall has begun. Now for it not to rain so we can have a fully bricked house by mid next week.
Wednesday, 16 January 2013
We have a roof
Saturday, 12 January 2013
Early January update
Just to provide an update, our bricks have been delayed as they need to get made and inspected. We're hopefully getting them mid-January, but our site supervisor (who has been great) has mentioned that he may try get our roof tiles done first so something is actually happening. Here's hoping! :)